Short Term Goals (Two Years): |
||
| Infrastructure | ||
| Jack Tone Road Interchange (completed) | Preliminary $22,000,000 | Matthew Machado, City Engineer |
| Frontage Road-Stockton Street to Jack Tone Road | Estimate $2,500,000 | Matthew Machado, City Engineer |
| Second Street Overpass Sidewalk (completed) | Estimate $200,000 | Matthew Machado, City Engineer |
|
Elevated Water Storage Reservoir (completed) |
Estimate $1,500,000 | Matthew Machado, City Engineer |
|
Parks and Recreation |
||
| City Skate Park (completed) | Bid $288,753 | Kye Stevens, Recreation Director |
| Mavis Stouffer Park Extension | Estimate $75,000 | Kye Stevens, Recreation Director |
| Swimming Pool-Joint
Venture with Ripon Unified School District (completed) |
Estimate $750,000 | Kye Stevens, Recreation Director |
| Neighborhood Park at Highland Avenue | Estimate $1,100,000 | Kye Stevens, Recreation Director |
| Expand Harvest Estates Park (completed) | Estimate $150,000 | Kye Stevens, Recreation Director |
|
Public Safety |
||
| Video Cameras in Police Units (completed) | Estimate $30,000 | Richard Bull, Chief of Police |
| Police Shooting Range (completed) | Estimate $10,000 | Richard Bull, Chief of Police |
| New Fire Station (completed) | Preliminary $3,000,000 | Financed By Redevelopment Agency |
|
Community Improvement |
||
| Stanislaus River Bicycle/Pedestrian Bridge (completed) | Estimate $1,500,000 | Matthew Machado, City Engineer |
| Animal Control Shelter (completed) | Estimate $230,000 | Matthew Machado, City Engineer |
|
Mid-Term Goals (3 - 6 Years): |
||
|
Infrastructure |
||
| Connection of Doak Blvd. and Stockton Street (completed) | Estimate $750,000 | Matthew Machado, City Engineer |
|
Parks and Recreation |
||
| 55 Acre Oak Grove Park Site | No Estimate | Kye Stevens, Recreation Director |
| Expand Boesch-Kingery Park | Estimate $600,000 | Kye Stevens, Recreation Director |
| River Road Regional Sports Complex | Estimate $9,000,000 | Kye Stevens, Recreation Director |
|
Public Safety |
||
| Installation of Computers in all Police Units (completed) | Estimate $70,000 | Richard Bull, Chief of Police |
| Joint Training
Facility: Police Department And Fire District |
No Estimate | Richard Bull,
Chief of Police and Ripon Consolidated Fire Chief |
|
Community Improvement |
||
| Rehabilitation of Old Municipal Building | Estimate $250,000 | Kye Stevens, Recreation Director |
| Long Term Goals (6 + Years): | ||
|
Infrastructure |
||
| Olive Road Interchange | Estimate $24,000,000 | Matthew Machado, City Engineer |
| Surface Water Treatment Facility | Estimate $10,000,000 | Matthew Machado, City Engineer |
|
Parks and Recreation |
||
| Stanislaus River Trail System | Estimate $400,000 | Kye Stevens, Recreation Director |
| Recreation Pool-Joint Venture with Ripon Unified School District (completed) | Estimate $1,500,000 | Kye Stevens, Recreation Director |
|
Public Safety |
||
| Police Facility | Estimate $6,400,000 | Richard Bull, Chief of Police |
|
Community Improvement |
||
| Expansion of Senior Citizens Center (completed) | Estimate $400,000 | Kye Stevens, Recreation Director |
| Community Center No. 2 | Estimate $7,500,000 | Kye Stevens, Recreation Director |
| New Library (completed) | Estimate $2,300,000 | Kye Stevens, Recreation Director |
| Performing Arts Center | No Estimate | Kye Stevens, Recreation Director |
|
|
||
back to |
||||
incentives |
|